The first call came at 4:18 PM on a Thursday. I answered because no one calls a quality manager with good news.
The commissioning manager didn’t bother with hello. “The BESS is throttling. We’re at 82% of rated power and it’s 47°C outside.”
My first thought was that the battery cells were bad. They weren’t. My second thought was that the supplier had cut a corner. They hadn’t, exactly. The system was doing what the contract allowed it to do.
I had found the enemy, and it was a vague specification.
A short background on who I am
A little context, in case it helps. I work in the quality and compliance function for Ørsted. I have reviewed wind turbine packages and storage equipment specifications since 2021. That is not a huge sample—maybe 50 procurement cycles and a few hundred factory acceptance reports. But I have seen the same gap recur in both technologies.
Let me say something up front: I don’t build batteries, and I don’t build wind turbines. Ørsted develops renewable energy projects. We buy equipment from specialists. That is not a weakness. It is exactly why we need precise specifications. If I claimed to know every cell chemistry detail, you shouldn’t trust me. If I write a contract that protects the performance we need, then I have done my job.
When I say “Ørsted wind turbines,” I don’t mean turbines made by Ørsted. I mean the turbines installed in Ørsted’s projects, supplied by specialist manufacturers. The quality problem is the same on that side: a datasheet is not a guarantee.
How the problem started
In 2025, we were evaluating several BESS wholesale offers for co-located storage on a renewable project. The shortlist came down to three manufacturers. The winner was not the cheapest by a wide margin, but the commercial package was stronger. We issued a detailed request for quotation with our own energy storage system specification guide—or, I should say, what we thought was detailed.
The guide had sections on safety, transportation, site conditions, grid code compliance, and testing. It referenced standards like UL 9540A and IEC 62933-5-2. The vendor submitted a compliant bid. We checked it. We pushed back on a few warranty clauses. We negotiated the price. Then we signed.
And that was when the real work should have begun.
One section of our spec said the system should “operate” at ambient temperatures up to 50°C. The manufacturer’s datasheet said -20°C to 55°C. Good, we thought. Done.
We had not specified what the system should do at 50°C. Did “operate” mean full rated power? Or did it mean “stay connected, charge at a reduced rate, avoid tripping”? In a BESS, those are completely different products.
At 47°C, the unit throttled output to 82% to keep the cells and conditioned air within limits. The BMS was not broken. It was doing exactly what it was designed to do. The system “operated.” It just didn’t deliver the power the project needed on a hot afternoon—which, it turned out, was the most valuable hour of the day.
Why does that matter? Because peak grid demand often lands in the same heat wave that drives prices up. If you are buying BESS wholesale for energy arbitrage, reserve products, or peak management, a high-temperature derating is not a footnote. It is the business case.
“We met spec”
The supplier’s response was calm and technically correct. It went something like:
“We supplied what the specification asked. The system’s operating ambient temperature range is met. Performance derating at high temperature is part of the thermal protection design. If you need full power at 47°C, we can provide that as an option.”
Read that again: it was an option. We had decided, by omission, not to buy it.
Looking back at the contract, our spec did say the BESS should deliver the specified AC power at site ambient temperature conditions. The problem was that it did not say what that meant at a specific temperature, at a specific state of charge, or for a specific duration.
The supplier’s thermal model treated 47°C as an exceptional condition. Our requirement did not clearly say that 47°C was not exceptional. A good engineer read the intent one way. A project manager read it another way. I was somewhere in the middle, and I should have caught it.
Maybe that sounds obvious in hindsight. It wasn’t at the time, because the safety test reports looked thorough and the price was under budget. I assumed standard performance testing would include site ambient conditions. Didn’t verify. Turned out it didn’t.
The retrofit cost about $180,000. The delay was three weeks. In the grand scheme of a large renewable project, not fatal. But it was unnecessary and embarrassing—especially because an avoidable design change becomes a change order that the supplier is in a much stronger position to price.
Not ideal. But an honest outcome.
What I changed in our energy storage system specification guide
After that project, I reworked the specification template. The most important change is simple: we no longer let the word “operate” survive on its own.
We now separate two requirements:
- Survival temperature: The system must remain safe, remain within warranty, and suffer no accelerated degradation if ambient temperature stays between X and Y for a defined period.
- Performance temperature: The AC output at the point of interconnection must equal or exceed the rated power when ambient temperature is a defined number, with the same auxiliary loads running, for the full required duration.
Here is a concrete sentence I now include. If you are comparing BESS manufacturers, you can steal this.
“At an ambient temperature of no more than 45°C measured at the container air intake, the BESS shall deliver the rated AC active power continuously at the point of interconnection with no more than 2% power tolerance and without entering a battery current-limiting mode. This shall be demonstrated by a witnessed system-level test across the full dispatchable state-of-charge range.”
That last phrase matters. A system can look great at 50% state of charge and then throttle at lower or higher states of charge. If you are buying dispatchable capacity, you need to know the whole operating range, not just the sales-friendly middle.
The best BESS manufacturer won’t argue with language like that. They will price it, and they will also tell you that the test costs money. Good. That is exactly the conversation you should be having before you sign, not after a hot afternoon exposes the gap.
Wind turbines have the same problem
The same pattern shows up with Ørsted wind turbines. A turbine supplier might say “power curve per IEC 61400-12” without explaining which air density, which turbulence intensity, or which measurement method applies. Those details can change annual energy production by several percent.
In 2025, the Ørsted renewable energy projects I worked on became more complex, not less. When storage is paired with wind, two different specialist suppliers each provide part of the overall plant. The contract between them becomes part of the system. My team had to specify not only equipment and testing, but also who owns performance when two different OEM systems interact.
That is a normal risk in our industry. I don’t say that to alarm you. I say it because vague language is the part you can fix before money moves.
This guide has boundaries
To be fair: my experience is based on utility-scale procurement for Ørsted projects. If you are buying a smaller commercial storage unit or a behind-the-meter system, parts of this guide will be overkill. The principle still applies: you are not buying a battery cell. You are buying predictable performance under the conditions where your project will actually operate.
Also remember that this was my experience as of early 2026. BESS technology, UL standards, IEC standards, and grid codes are moving quickly. Verify the current requirements before you copy anything into a contract. What I am confident about is not the chemistry or the code reference. It is the rule underneath: specify the outcome you need, in the conditions that actually exist, and make someone test it.
If a supplier says “trust us, we do everything,” that is not a specification. If they say “we need clarity on what full power means at 45°C,” that is a sign you are finally having the right conversation.
I still answer phone calls at 4:18 PM. Now I ask a different question first: “What exactly did the contract say?”